Replacing siding feels like an exterior facelift, so many owners assume no permit is needed. In Hollywood that assumption usually turns out to be wrong. The city's Building Division enforces the Florida Building Code, and a new skin on an exterior wall in Broward County is treated as building work, not decoration. This guide covers what we could confirm from the city's own pages and what to check with the Building Division before work starts.
The short answer
Plan on a permit. The City of Hollywood's permit FAQ says a building permit is needed to construct, enlarge, alter, repair, move, remove or demolish any building or structure, and taking off and replacing siding alters an exterior wall. The same FAQ asks anyone unsure whether their project needs a permit to contact the Building Division, which is the right step for small patch repairs where the answer may differ.
Why siding is more than cosmetic here
Broward County is part of the Florida Building Code's High-Velocity Hurricane Zone. In that zone, cladding has to resist set wind loads, and a panel that tears loose becomes flying debris for the house next door. That is why the code cares about the product used and how it is fastened, not only whether the wall looks finished.
Removing siding also exposes the sheathing and the water barrier behind it. A permit gives an inspector the chance to see that work before it is covered again. The same thinking applies whatever the new material is, vinyl, fiber cement or engineered wood, because each one has its own approved fastening pattern.
Who applies for the permit
Most of the time the contractor doing the work applies for the permit and is named on it. Ask about this before you sign, and be wary of anyone who suggests skipping it to save time.
Hollywood also allows owner-builder permits. According to the city's FAQ, an owner can apply as long as they own the one-family or two-family home and it is for their own use or occupancy. Taking that route makes you responsible for the work meeting code and passing inspection, which is a lot to take on for a full re-side.
How applications are filed now
Hollywood changed its system this year. The city's permits page says that from August 4, 2026, all new permit applications go through the Accela Citizen Access portal. Applicants create an account before applying, and contractors register or update their details in the same portal before they can be linked to a permit.
Permits opened under the older system follow different instructions, so if your project started before the change, check which process applies.
What the application usually includes
The city's own checklist is the final word, so confirm it with the Building Division. On a typical re-siding permit in South Florida, expect to provide:
- A description of the work and the walls being re-sided.
- The product approval for the siding, showing it may be used in the High-Velocity Hurricane Zone.
- The manufacturer's installation instructions that match that approval.
- Details of the water barrier and flashing, and any sheathing repair planned.
Inspections during the job
The permit will spell out which inspections apply. The practical rule is simple: nothing gets covered until the inspection that needs to see it has passed. If the city wants to see the barrier or fastening before the siding goes up, the schedule has to allow for it.
The Building Division's main page notes that inspections can be scheduled online. The job is closed out with a final inspection.
What happens if work is done without a permit
Unpermitted exterior work tends to surface at the worst time. It can come up when you sell and a buyer's inspector or title search asks about it, or when an insurer looks at storm damage. Fixing it after the fact can mean applying late and opening finished walls so an inspector can see what is behind them. A permit at the start costs far less trouble.
Older homes and special areas
On an older house, tear-off often turns up soft sheathing, rot under window sills or old termite damage that has to be repaired before new siding goes on. Tell the Building Division about it if the permit did not already cover that repair, and keep photos of what was found and fixed. They are useful later, for an inspector, an insurer or a future buyer.
If your property is in a designated historic district or has other special zoning, ask the city whether a design review applies before you settle on a material or profile.
Before you start
Call or email the Building Division with your address and a short description of the work, and get your answer in writing if you can. Our siding contractor services for Hollywood page covers local housing, climate and costs, and the siding replacement page explains what a full re-side involves from tear-off to final inspection.